Project Scope: 

 

This project involved the design of a new industrial subdivision on approximately 35 hectares of land located at the Southwest corner of Line 61 and Perth Road 131 in Milverton, Ontario. We developed a unique servicing strategy for this subdivision. We designed a STEP (Septic Tank Effluent Pump) system, with on-lot primary treatment, which had an outlet directly into the lagoons located off Line 61.  

 

Since the area had inadequate municipal fire flow, we incorporated an on-site fire reservoir and dedicated fire pump station, as well as extending the domestic watermain from County Road 131.  

 

The Stormwater control was completed by a wet pond and forebay, with enhanced grass swales for pre-treatment.  

 

Due to the road crossing an existing open ditch municipal drain a large concrete box culvert was installed at the road crossing.  

 

The work included: 

  • 1,340m of road construction 

  • a stormwater management pond 

  • a fire reservoir/pumping station 

  • 1,420m of storm sewer 

  • 1,910m of sanitary forcemain,  

  • 3,435m of watermain (Fire & Domestic) 

This industrial subdivision has been partially built out, with some lots left ready for site plan development.  

 

Project Details:

 

Date of Completion: September 2024